How Does Our Swimming Pool Get Installed?
Fiberglass swimming pools have the shortest installation time compared to other styles. The basic installation timeline is 2-5 weeks depending on weather and complexity of the project. Stages shown below are what you can expect during installation.
Step One- Layout
Step Two- Pool Delivery
Step Three- Excavation and Pool Base
Once the initial renderings are approved by the customer we can layout the pool in paint. Before any layouts can begin J.U.L.I.E will need to mark underground utilities. Most permits can not be approved until inspector can verify compliance with pool placement to easements and utilities.
Pool arrival, at this point the excavator will remove the pool from the trailer. It will be placed out of the way until the excavation is complete and the pool gravel base is established.
We can break ground and start hauling away spoils from the site. Once site excavation is complete we can set up guides and level the gravel pool base.
Step Four- Pool Setting / Back-filling / Adding Water
Step Five- Plumbing / Utility Rough In
Step Six- Assemble Forms For Concrete
The pool can be lowered into the hole, we will make sure that the pool is sitting level. This can take a few times to get right by lifting the pool and shifting the gravel underneath if needed. The pool will need to be filled while back filling voids around the pool. This will insure the integrity of the pool shell until the pool is completely back filled.
Step Seven- Pour Concrete Deck
Step Eight- Form Removal
Step Nine- Equipment Hookup
Step Ten- New Pool Orientation